Federal Court Rejects Attempts To Reopen Summary Judgment in Florida Construction Defect Dispute

Construction disputes often focus on engineering questions, contract terms, and project management decisions. But sometimes, winning a case comes down to something more basic: meeting the court’s deadlines.
A recent federal case in Florida makes that point very clear. In a case between Orlando Health, Inc. and HKS Architects, Inc., the court refused to revisit a summary judgment after one side simply missed its response deadline. The message this case sends is that even a small procedural mistake can have big consequences in construction litigation.
At Bleakley Bavol Denman & Grace, we work closely with contractors, developers, architects, and property owners all across Florida. Whether you’re dealing with design defects, project delays, or construction claims that end up in federal court, we understand the process and are here to support you.
Missed Deadline Leads To Adverse Ruling
In this case, the dispute arose out of a hospital construction project in Orlando. Orlando Health sued HKS Architects, who then brought BBM Structural Engineers into the lawsuit as a third-party defendant. The underlying case involved allegations that structural issues discovered during construction were design-related defects rather than construction errors.
During litigation, Orlando Health filed a motion for summary judgment on HKS’s affirmative defenses. According to the court’s scheduling rules, HKS had 21 days to respond. However, they missed that window. The court granted the motion, and the case moved forward.
Over two months later, HKS asked the court to set aside that decision, arguing the failure to respond was due to “excusable neglect” caused by a calendaring and administrative oversight. HKS also argued that the delay wasn’t intentional and that they should be given another chance to respond.
Court Found No “Excusable Neglect”
The court rejected HKS’s request. In fact, the judge said HKS’s internal error was entirely within their control, and the delay was too long. Courts have the power to revisit non-final orders, but relief is not automatic. You have to show that you acted with diligence and fairness. The court also noted that reopening the issue would disrupt an upcoming trial schedule.
Court Also Rejected Attempt To Revise Factual Language
Meanwhile, BBM Structural Engineers, as a third party, asked the court to reconsider some language in the earlier order referring to “design defects.” They felt the court had improperly made factual findings before the trial even started.
The court disagreed, pointing out that this language had been used before without complaint. The court also clarified that since the case was headed for a bench trial (where the judge, not a jury, decides the facts), there was no harm. The order didn’t resolve liability issues, so the judge saw no reason to change it.
Key Takeaways for Florida Construction Cases
This ruling highlights several important lessons for construction litigation in Florida, including the following:
- Missing a response deadline can result in serious and sometimes irreversible procedural consequences.
- Courts rarely reopen rulings based on internal office mistakes or administrative errors.
- Temporary orders can be revised, but only when there is strong justification and diligence.
Contact Us for Legal Help
If you’re facing a construction dispute, you shouldn’t go at it alone. Any procedural mistake can affect your case. Our Tampa construction litigation attorneys at Bleakley Bavol Denman & Grace are ready to help you protect your rights. Contact our office today to schedule a consultation and discuss your case.
Source:
scholar.google.com/scholar_case?case=6561058211138130669&q=Defective+construction+litigation&hl=en&as_sdt=4,10,325,326,327&as_ylo=2026